NGCP Scheduled Power Interruption
PAUNAWA
Ano: NGCP Scheduled Power Interruption
Kailan: Nobyembre 19, 2021 (Biyernes)
Oras: Sa pagitan ng 3:00 ng umaga hanggang 11:00 ng umaga (mga 8 na oras)
Mga Apektadong Lugar:
GUAGUA – Lahat ng barangay
SASMUAN – Lahat ng barangay
LUBAO – Lahat ng barangay
STA. RITA – Brgy. San Vicente, San Jose, San Juan, San Isidro, San Basilio, Sta. Monica, San Agustin, San Matias, Dila Dila (ilang bahagi) at Becuran (maliban sa Becuran High School Highway)
BACOLOR – Lahat ng barangay maliban sa Calibutbut at Maliwalu
PORAC – Brgy. Salu at Balubad (Purok 6 at 7)
FLORIDABLANCA – Brgy. Gutad at ilang bahagi ng Anon
Dahilan:
– Testing & Commissioning of Deluge Water Spray Fire Protection System for 300 MVA T1;
– Correction of critical hotspot at A-DS03 (5LI1HER-DLU) HER & C-DS03 (5LI1HER-BLN) HER, 69kV bus side Hermosa Substation;
– Alignment & Installation of conductors for new 5Z-03DS23HER (bus side & breaker side), in preparation for transferring of Hermosa—Guagua 69kV line to new bay 3 of breaker and a half scheme;
– Raising of conductors at span #91— 92 and TL maintenance along Hermosa—Guagua 69kV line;
– Installation of temporary feeder metering at Sta. Cruz Substation;
– Substation Works;
– O&M works; and
– R.O.W / Clearing of lines
Para sa kaalaman ng lahat.